This summer, we are going to be doing three projects/improvements to your system. We will be replacing all ten of our original pressure reducing valves (PRV), we will be replacing 15-20 original gate valves throughout the system as well as a mile and a half of pipeline. The third project will be adding a 200,000 gallon underground storage reservoir at our treatment plant north of Hannaford. We ask for your patience as we complete these projects. There will be times that some of our customers will be without water. We will do our best to let you know when the outages are going to happen.
-
PRV Replacement
End of June-first part of July
-
Gate valve and line replacement
End of June- first part of July
-
Reservoir Expansion
August-September